Volumn 4, Issue , 2011, Pages 6218-6225

Dual-track CCS stakeholder engagement: Lessons learned from FutureGen in Illinois

Author keywords

Carbon capture and storage; CCS; Engagement; Public acceptance; Public perception; Site selection process; Stakeholder involvement

Indexed keywords

COAL; COAL INDUSTRY; COAL STORAGE; ELECTRIC UTILITIES; FOSSIL FUEL POWER PLANTS; GREENHOUSE GASES; SITE SELECTION;

EID: 79955413503     PISSN: 18766102     EISSN: None     Source Type: Conference Proceeding    
DOI: 10.1016/j.egypro.2011.02.634     Document Type: Conference Paper
Times cited : (9)

References (7)
  • 1
    • 85031275529 scopus 로고    scopus 로고
    • Prepared for the U.S. Department of Energy by the FutureGen Alliance. Available at
    • FutureGen Alliance. 2006. "Results of Site Offeror Proposal Evaluation." Prepared for the U.S. Department of Energy by the FutureGen Alliance. Available at: http://www.futuregenalliance.org/publications/fg- proposal-evaluation-report.pdf.
    • (2006) Results of Site Offer or Proposal Evaluation
  • 2
    • 84871808270 scopus 로고    scopus 로고
    • See, website at
    • See FutureGen Alliance website at http://www.futuregenalliance.org.
    • FutureGen Alliance
  • 3
    • 84874202673 scopus 로고    scopus 로고
    • Community acceptance of carbon capture and sequestration infrastructure: Siting challenges
    • Parfomak PW. 2008. Community Acceptance of Carbon Capture and Sequestration Infrastructure: Siting Challenges. CRS Report for Congress.
    • (2008) CRS Report for Congress
    • Parfomak, P.W.1
  • 5
    • 79955411733 scopus 로고    scopus 로고
    • Personal stakeholder communication, June 22, 2010, Mattoon, IL
    • Personal stakeholder communication. 2010. FutureGen site planning meeting, June 22, 2010, Mattoon, IL.
    • (2010) FutureGen Site Planning Meeting
  • 6
    • 79955411733 scopus 로고    scopus 로고
    • Personal stakeholder communication, June 22, 2010, Mattoon, IL
    • Personal stakeholder communication. 2010. FutureGen site planning meeting, June 22, 2010, Mattoon, IL.
    • (2010) FutureGen Site Planning Meeting
  • 7
    • 79955411733 scopus 로고    scopus 로고
    • Personal stakeholder communication, June 22, 2010, Mattoon, IL
    • Personal stakeholder communication. 2010. FutureGen site planning meeting, June 22, 2010, Mattoon, IL.
    • (2010) FutureGen Site Planning Meeting


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.