Volumn 38, Issue 5, 2011, Pages 809-815

Minimization of maximum lateness on parallel machines with sequence-dependent setup times and job release dates

Author keywords

Iterated greedy heuristic; Maximum lateness; Parallel machines scheduling problems; Sequence dependent setup times

Indexed keywords

BENCH-MARK PROBLEMS; COMPUTATIONAL EXPERIMENT; DATA SETS; IDENTICAL PARALLEL MACHINES; ITERATED GREEDY HEURISTIC; MAXIMUM LATENESS; OTHER APPLICATIONS; PARALLEL MACHINE; PARALLEL MACHINES SCHEDULING PROBLEM; RELEASE DATE; SEQUENCE-DEPENDENT SETUP TIME;

EID: 78149280439     PISSN: 03050548     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.cor.2010.09.020     Document Type: Article
Times cited : (41)

References (16)
  • 6
    • 0029404198 scopus 로고
    • Rolling horizon procedures for dynamic parallel machine scheduling with sequence-dependent setup times
    • I.M. Ovacik, and R. Uzsoy Rolling horizon procedures for dynamic parallel machine scheduling with sequence-dependent setup times International Journal of Production Research 33 1995 3173 3192
    • (1995) International Journal of Production Research , vol.33 , pp. 3173-3192
    • Ovacik, I.M.1    Uzsoy, R.2
  • 9
    • 0013148980 scopus 로고
    • A local-search heuristic for large set-covering problems
    • L.W. Jacobs, and M.J. Brusco A local-search heuristic for large set-covering problems Naval Research Logistics Quarterly 42 1995 1129 1140
    • (1995) Naval Research Logistics Quarterly , vol.42 , pp. 1129-1140
    • Jacobs, L.W.1    Brusco, M.J.2
  • 10
    • 84958631348 scopus 로고    scopus 로고
    • An evolutionary algorithm for large scale set covering problems with application to airline crew scheduling
    • E. Marchiori, and A. Steenbeek An evolutionary algorithm for large scale set covering problems with application to airline crew scheduling Lecture Notes in Computer Science 1803 2000 367 381
    • (2000) Lecture Notes in Computer Science , vol.1803 , pp. 367-381
    • Marchiori, E.1    Steenbeek, A.2
  • 11
    • 33750841084 scopus 로고    scopus 로고
    • A simple and effective iterated greedy algorithm for the permutation flowshop scheduling problem
    • R. Ruiz, and T. Sttzle A simple and effective iterated greedy algorithm for the permutation flowshop scheduling problem European Journal of Operational Research 177 2007 2033 2049
    • (2007) European Journal of Operational Research , vol.177 , pp. 2033-2049
    • Ruiz, R.1    Sttzle, T.2
  • 12
    • 34548509933 scopus 로고    scopus 로고
    • A note on a greedy heuristic for flow-shop makespan minimization with no machine idle-time
    • D. Baraz, and G. Mosheiov A note on a greedy heuristic for flow-shop makespan minimization with no machine idle-time European Journal of Operational Research 184 2008 810 813
    • (2008) European Journal of Operational Research , vol.184 , pp. 810-813
    • Baraz, D.1    Mosheiov, G.2
  • 13
    • 37049022197 scopus 로고    scopus 로고
    • An Iterated Greedy heuristic for the sequence dependent setup times flowshop problem with makespan and weighted tardiness objectives
    • R. Ruiz, and T. Sttzle An Iterated Greedy heuristic for the sequence dependent setup times flowshop problem with makespan and weighted tardiness objectives European Journal of Operational Research 187 2008 1143 1159
    • (2008) European Journal of Operational Research , vol.187 , pp. 1143-1159
    • Ruiz, R.1    Sttzle, T.2
  • 14
    • 49349104489 scopus 로고    scopus 로고
    • Solving non-permutation flowshop scheduling problems by an effective iterated greedy heuristic
    • K.C. Ying Solving non-permutation flowshop scheduling problems by an effective iterated greedy heuristic International Journal of Advanced Manufacturing Technology 38 2008 348 354
    • (2008) International Journal of Advanced Manufacturing Technology , vol.38 , pp. 348-354
    • Ying, K.C.1
  • 15
    • 67449115947 scopus 로고    scopus 로고
    • An iterated greedy heuristic for multistage hybrid flowshop scheduling problems with multiprocessor tasks
    • K.C. Ying An iterated greedy heuristic for multistage hybrid flowshop scheduling problems with multiprocessor tasks Journal of the Operational Research 60 2009 810 817
    • (2009) Journal of the Operational Research , vol.60 , pp. 810-817
    • Ying, K.C.1
  • 16
    • 58349107029 scopus 로고    scopus 로고
    • Sequencing single-machine tardiness problems with sequence dependent setup times using an iterated greedy heuristic
    • K.C. Ying, S.W. Lin, and C.Y. Huang Sequencing single-machine tardiness problems with sequence dependent setup times using an iterated greedy heuristic Expert Systems with Applications 36 2009 7087 7092
    • (2009) Expert Systems with Applications , vol.36 , pp. 7087-7092
    • Ying, K.C.1    Lin, S.W.2    Huang, C.Y.3


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.