Volumn 38, Issue 7, 2010, Pages 3164-3173

"Take the long way down": Integration of large-scale North Sea wind using HVDC transmission

Author keywords

Congestion management; HVDC connections; Wind energy

Indexed keywords

CONGESTION MANAGEMENT; ELECTRICITY GENERATION; ENGINEERING STANDPOINT; GERMANY; GRID EXTENSION; HIGH VOLTAGE DIRECT CURRENT; HVDC TRANSMISSION; LOAD CENTERS; NETWORK EXTENSIONS; NETWORK MODELS; NODAL PRICING; NORTH SEA; OFFSHORE WIND RESOURCES; PRICE SIGNALS; SOUTHERN GERMANY; UNIFORM PRICING; WIND ENERGY;

EID: 77952374721     PISSN: 03014215     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.enpol.2009.07.041     Document Type: Article
Times cited : (60)

References (27)
  • 2
    • 77953684893 scopus 로고    scopus 로고
    • Bafa, 〈〉 (retrieved 11.08.2008).
    • Bafa, 2008. 〈〉 (retrieved 11.08.2008). http://www.bafa.de/bafa/de/energie/index.html.
    • (2008)
  • 3
    • 0027461030 scopus 로고
    • Short and long-run elasticities in energy demand-a cointegration approach
    • Bentzen J., Engsted T. Short and long-run elasticities in energy demand-a cointegration approach. Energy Economics 1993, 15(1):9-16.
    • (1993) Energy Economics , vol.15 , Issue.1 , pp. 9-16
    • Bentzen, J.1    Engsted, T.2
  • 4
    • 77952331385 scopus 로고    scopus 로고
    • Dimensoring of cables for grid connection of offshore wind farms taking into account the time factor of energy production
    • Brakelmann H., Richert F. Dimensoring of cables for grid connection of offshore wind farms taking into account the time factor of energy production. DEWI-Magazin 2004, 24:3843.
    • (2004) DEWI-Magazin , vol.24 , pp. 3843
    • Brakelmann, H.1    Richert, F.2
  • 5
    • 77953687044 scopus 로고    scopus 로고
    • An International Comparison of Models for Measuring Market Power in Electricity, Stanford University, Stanford, Working Paper EMF WP 17.1.
    • Bushnell, J., Day, Ch., et al., 1999: An International Comparison of Models for Measuring Market Power in Electricity, Stanford University, Stanford, Working Paper EMF WP 17.1.
    • (1999)
    • Bushnell, J.1    Day, Ch.2
  • 6
    • 41849128513 scopus 로고    scopus 로고
    • Comparison of feed-in tariff, quota and auction mechanisms to support wind power development
    • Butler L., Neuhoff K. Comparison of feed-in tariff, quota and auction mechanisms to support wind power development. Renewable Energy 2008, 33(8):1854-1867.
    • (2008) Renewable Energy , vol.33 , Issue.8 , pp. 1854-1867
    • Butler, L.1    Neuhoff, K.2
  • 7
    • 77953685236 scopus 로고    scopus 로고
    • Dena, Dena-Netzstudie, Energiewirtschaftliche Planung für die Netzintegration von Windenergie in Deutschland an Land und Offshore bis zum Jahr 2020. Deutsche Energie-Agentur.
    • Dena, 2005. Dena-Netzstudie, Energiewirtschaftliche Planung für die Netzintegration von Windenergie in Deutschland an Land und Offshore bis zum Jahr 2020. Deutsche Energie-Agentur.
    • (2005)
  • 8
    • 77953685822 scopus 로고    scopus 로고
    • DLR, Trans-Mediterranean Interconnection for Concentrating Solar Power. Study commissioned by Federal Ministry for the Environment, Nature Conservation and Nuclear Safety Germany.
    • DLR, 2006. Trans-Mediterranean Interconnection for Concentrating Solar Power. Study commissioned by Federal Ministry for the Environment, Nature Conservation and Nuclear Safety Germany.
    • (2006)
  • 9
    • 77953684400 scopus 로고    scopus 로고
    • DWD. Datenabgabe 439/05, Wind Speed Information about 8 Stations. German Weather Service (DWD).
    • DWD. 2005. Datenabgabe 439/05, Wind Speed Information about 8 Stations. German Weather Service (DWD).
    • (2005)
  • 10
    • 77953685497 scopus 로고    scopus 로고
    • Eurostat, 〈〉 (retrieved 09.01.2006).
    • Eurostat, 2005. 〈〉 (retrieved 09.01.2006). http://epp.eurostat.cec.eu.int/portal/page?_pageid=1996,45323734&_dad=portal&_schema=PORTAL&screen=welcomeref&open=/&product=EU_MASTER_regions&depth=2.
    • (2005)
  • 12
    • 33947141570 scopus 로고    scopus 로고
    • Nodal pricing of electricity: how much does it cost to get it wrong?
    • Green R. Nodal pricing of electricity: how much does it cost to get it wrong?. Journal of Regulatory Economics 2007, 31(2):125-149.
    • (2007) Journal of Regulatory Economics , vol.31 , Issue.2 , pp. 125-149
    • Green, R.1
  • 13
    • 77952330804 scopus 로고    scopus 로고
    • Large-scale wind power in European electricity markets: time for revisiting support schemes and market designs, Energy Policy, this issue, doi:10.1016/j.enpol.2009.07.030.
    • Hiroux, C., Saguan, M., Large-scale wind power in European electricity markets: time for revisiting support schemes and market designs, Energy Policy, this issue, doi:10.1016/j.enpol.2009.07.030.
    • Hiroux, C.1    Saguan, M.2
  • 14
    • 34249835223 scopus 로고
    • Contract networks for electric power transmission
    • Hogan W.W. Contract networks for electric power transmission. Journal of Regulatory Economics 1992, 4:211-242.
    • (1992) Journal of Regulatory Economics , vol.4 , pp. 211-242
    • Hogan, W.W.1
  • 15
    • 77953686023 scopus 로고    scopus 로고
    • ISET-IWET, Räumliche Verteilung der installierten Nennleistung (Planflächen). 〈〉 (retrieved 09.01.2006).
    • ISET-IWET, 2002. Räumliche Verteilung der installierten Nennleistung (Planflächen). 〈〉 (retrieved 09.01.2006). http://reisi.iset.uni-kassel.de/pls/w3reisidad/www_reisi_page.show_menu?p_name=121017&p_lang=ger.
  • 16
    • 51649094501 scopus 로고    scopus 로고
    • Pros and cons of exposing renewables to electricity market risks-a comparison of the market integration approaches in Germany, Spain, and the UK
    • Klessmann C., Nabe C., Burges K. Pros and cons of exposing renewables to electricity market risks-a comparison of the market integration approaches in Germany, Spain, and the UK. Energy Policy 2008, 36:3646-3661.
    • (2008) Energy Policy , vol.36 , pp. 3646-3661
    • Klessmann, C.1    Nabe, C.2    Burges, K.3
  • 17
    • 77953684216 scopus 로고    scopus 로고
    • 31.4 GW Planned for Germany. Platts (2006): Power in Europe. Issue 486.
    • Knight, S. 2006. 31.4 GW Planned for Germany. Platts (2006): Power in Europe. Issue 486.
    • (2006)
    • Knight, S.1
  • 18
    • 77953687210 scopus 로고    scopus 로고
    • a. ELMOD-a model of the European electricity market. Chair of Energy Economics and Public Sector Management Dresden, Working Paper WP-EM-00.
    • Leuthold, F., Weigt, H., Hirschhausen, C.v., 2008a. ELMOD-a model of the European electricity market. Chair of Energy Economics and Public Sector Management Dresden, Working Paper WP-EM-00.
    • (2008)
    • Leuthold, F.1    Weigt, H.2    Hirschhausen, C.v.3
  • 19
    • 54049137280 scopus 로고    scopus 로고
    • Efficient pricing for European electricity networks-the theory of nodal pricing applied to feeding-in wind in Germany
    • Leuthold F., Weigt H., Hirschhausen C.v. Efficient pricing for European electricity networks-the theory of nodal pricing applied to feeding-in wind in Germany. Utilities Policy 2008, 16:284-291.
    • (2008) Utilities Policy , vol.16 , pp. 284-291
    • Leuthold, F.1    Weigt, H.2    Hirschhausen, C.3
  • 20
    • 77953687889 scopus 로고    scopus 로고
    • High Voltage Direct Current (HVDC) Transmission Systems-Technology Review Paper presented at Energy Week 2000, Washington, D.C., USA, March 7-8.
    • Rudervall, R., Charpentier, J.P., Raghuveer, S., 2000. High Voltage Direct Current (HVDC) Transmission Systems-Technology Review Paper presented at Energy Week 2000, Washington, D.C., USA, March 7-8.
    • (2000)
    • Rudervall, R.1    Charpentier, J.P.2    Raghuveer, S.3
  • 22
    • 51749096006 scopus 로고    scopus 로고
    • Optimization of the Austrian Electricity Sector (Control Zone of VERBUND APG) under the Constraints of Network Capacities by Nodal Pricing. Central European
    • Stigler H., Todem C. Optimization of the Austrian Electricity Sector (Control Zone of VERBUND APG) under the Constraints of Network Capacities by Nodal Pricing. Central European. Journal of Operations Research 2005, 13:105-125.
    • (2005) Journal of Operations Research , vol.13 , pp. 105-125
    • Stigler, H.1    Todem, C.2
  • 25
    • 77953688014 scopus 로고    scopus 로고
    • UCTE, Consumption Data. From: 〈〉 (Retrieved 19.01.2007).
    • UCTE, 2006. Consumption Data. From: 〈〉 (Retrieved 19.01.2007). http://www.ucte.org/statistics/onlinedata/consumption/edefault.asp.
    • (2006)
  • 26
    • 77953686582 scopus 로고    scopus 로고
    • VET, Geschäftsbericht 2007, Vattenfall Europe Transmission, Berlin. From: 〈〉 (retrieved 11.06.2009).
    • VET, 2008. Geschäftsbericht 2007, Vattenfall Europe Transmission, Berlin. From: 〈〉 (retrieved 11.06.2009). http://www.vattenfall.de/cps/rde/xbcr/trm_de/geschaeftsbericht200_60127.pdf.
    • (2008)


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.