Volumn 29, Issue 3, 2010, Pages 442-458
|
Stability analysis and reinforcement design of high and steep slopes with complex geology in abutment of Jinping I hydropower station
|
Author keywords
Deep unloading; Excavation control; Jinping I hydropower station; Monitoring feedback; Reinforcement design; Slope engineering; Slope structure; Stability analysis
|
Indexed keywords
EXCAVATION CONTROL;
JINPING I HYDROPOWER STATION;
REINFORCEMENT DESIGN;
SLOPE ENGINEERING;
SLOPE STRUCTURE;
STABILITY ANALYSIS;
ABUTMENTS (BRIDGE);
ARCH DAMS;
ARCHES;
BLASTING;
CONCRETE DAMS;
FAILURE ANALYSIS;
HYDRAULIC STRUCTURES;
HYDROELECTRIC POWER;
HYDROELECTRIC POWER PLANTS;
QUALITY ASSURANCE;
QUALITY CONTROL;
REINFORCEMENT;
ROCK MECHANICS;
ROCKS;
SAFETY ENGINEERING;
SLOPE PROTECTION;
STRUCTURAL DESIGN;
SYSTEM STABILITY;
UNLOADING;
SLOPE STABILITY;
|
EID: 77951651693
PISSN: 10006915
EISSN: None
Source Type: Journal
DOI: None Document Type: Article |
Times cited : (44)
|
References (13)
|