Volumn 48, Issue 6, 2010, Pages 1639-1651

Minimising makespan on parallel machines with precedence constraints and machine eligibility restrictions

Author keywords

Heuristics; Machine eligibility; Parallel machine; Precedence constraints; Scheduling; Shipbuilding

Indexed keywords

LOWER BOUNDS; MACHINE ELIGIBILITY; MACHINE ELIGIBILITY RESTRICTIONS; MACHINE LOADS; MAKESPAN; PARALLEL MACHINE; PARALLEL MACHINE-SCHEDULING PROBLEMS; PRECEDENCE CONSTRAINTS;

EID: 74549151667     PISSN: 00207543     EISSN: 1366588X     Source Type: Journal    
DOI: 10.1080/00207540802620779     Document Type: Article
Times cited : (34)

References (24)
  • 1
    • 33745192598 scopus 로고    scopus 로고
    • On a parallel machine scheduling problem with precedence constraints
    • Aho, I. and Makinen, E., 2006. On a parallel machine scheduling problem with precedence constraints. Journal of Scheduling, 9 (5), 493-495.
    • (2006) Journal of Scheduling , vol.9 , Issue.5 , pp. 493-495
    • Aho, I.1    Makinen, E.2
  • 2
    • 1242265218 scopus 로고    scopus 로고
    • Minimizing makespan on parallel machines with release time and machine eligibility restrictions
    • Centeno, G. and Armacost, R.L., 2004. Minimizing makespan on parallel machines with release time and machine eligibility restrictions. International Journal of Production Research, 42 (6), 1243-1256.
    • (2004) International Journal of Production Research , vol.42 , Issue.6 , pp. 1243-1256
    • Centeno, G.1    Armacost, R.L.2
  • 3
    • 0013027033 scopus 로고    scopus 로고
    • An efficient approximation algorithm for minimizing makespan on uniformly related machines
    • Chekuri, C., 2001. An efficient approximation algorithm for minimizing makespan on uniformly related machines. Journal ofAlgorithms, 41 (2), 212-224.
    • (2001) Journal ofAlgorithms , vol.41 , Issue.2 , pp. 212-224
    • Chekuri, C.1
  • 4
    • 0025474221 scopus 로고
    • A state-of-the-art review of parallel machine scheduling research
    • Cheng, T.C.E. and Sin, C.C.S., 1990. A state-of-the-art review of parallel machine scheduling research. European Journal of Operational Research, 47 (3), 271-292.
    • (1990) European Journal of Operational Research , vol.47 , Issue.3 , pp. 271-292
    • Cheng, T.C.E.1    Sin, C.C.S.2
  • 5
    • 0031641788 scopus 로고    scopus 로고
    • Integrated process planning and scheduling systems for block assembly in shipbuilding
    • Cho, K.K., et al., 1998. Integrated process planning and scheduling systems for block assembly in shipbuilding. CIRP Annals Manufacturing Technology, 47 (1), 419-422.
    • (1998) CIRP Annals Manufacturing Technology , vol.47 , Issue.1 , pp. 419-422
    • Cho, K.K.1
  • 6
    • 0034957508 scopus 로고    scopus 로고
    • A spatial scheduling system for block painting process in shipbuilding
    • Cho, K.K., et al., 2001. A spatial scheduling system for block painting process in shipbuilding. CIRP Annals Manufacturing Technology, 50 (1), 339-342.
    • (2001) CIRP Annals Manufacturing Technology , vol.50 , Issue.1 , pp. 339-342
    • Cho, K.K.1
  • 7
    • 34247131354 scopus 로고    scopus 로고
    • Looking-forward scheduling approach applied in pre-erection area of a shipyard
    • Duck, Y.Y. and Ranjan, V., 2007. Looking-forward scheduling approach applied in pre-erection area of a shipyard. Journal ofShip Production, 23 (1), 30-35.
    • (2007) Journal ofShip Production , vol.23 , Issue.1 , pp. 30-35
    • Duck, Y.Y.1    Ranjan, V.2
  • 8
    • 0031275738 scopus 로고    scopus 로고
    • Heuristics for unrelated machine scheduling with precedence constraints
    • Herrmann, J., Proth, J.-M., and Sauer, N., 1997. Heuristics for unrelated machine scheduling with precedence constraints. European Journal of Operational Research, 102 (3), 528-537.
    • (1997) European Journal of Operational Research , vol.102 , Issue.3 , pp. 528-537
    • Herrmann, J.1    Proth, J.-M.2    Sauer, N.3
  • 9
    • 0035681031 scopus 로고    scopus 로고
    • List scheduling in a parallel machine environment with precedence constraints and setup times
    • Hurink, J. and Knust, S., 2001. List scheduling in a parallel machine environment with precedence constraints and setup times. Operational Research Letters, 29 (5), 231-239.
    • (2001) Operational Research Letters , vol.29 , Issue.5 , pp. 231-239
    • Hurink, J.1    Knust, S.2
  • 10
    • 0036374260 scopus 로고    scopus 로고
    • Applying digital manufacturing technology to ship production and the martime environment
    • Kim, H., et al., 2002. Applying digital manufacturing technology to ship production and the martime environment. Integrated Manufacturing Systems, 13 (5), 295-305.
    • (2002) Integrated Manufacturing Systems , vol.13 , Issue.5 , pp. 295-305
    • Kim, H.1
  • 11
    • 32144460178 scopus 로고    scopus 로고
    • A model for a simulation-based shipbuilding system in a shipyard manufacturing process
    • Kim, H., et al., 2005. A model for a simulation-based shipbuilding system in a shipyard manufacturing process. International Journal of Computer Integrated manufacturing, 18 (6), 427-441.
    • (2005) International Journal of Computer Integrated manufacturing , vol.18 , Issue.6 , pp. 427-441
    • Kim, H.1
  • 12
    • 0031103567 scopus 로고    scopus 로고
    • Developing scheduling systems for Daewoo Shipbuilding: DAS project
    • Lee, J.K., et al., 1997. Developing scheduling systems for Daewoo Shipbuilding: DAS project. European Journal Operation Research, 97 (2), 380-395.
    • (1997) European Journal Operation Research , vol.97 , Issue.2 , pp. 380-395
    • Lee, J.K.1
  • 13
    • 33745188709 scopus 로고
    • Complexity of scheduling under precedence constraints
    • Lenstra, J.K. and Rinnooy Kan, A.H.G., 1987. Complexity of scheduling under precedence constraints. Operations Research, 26 (1), 23-35.
    • (1987) Operations Research , vol.26 , Issue.1 , pp. 23-35
    • Lenstra, J.K.1    Rinnooy Kan, A.H.G.2
  • 14
    • 34548502246 scopus 로고    scopus 로고
    • Parallel machine scheduling with machine availability and eligibility constraints
    • Liao, L.-W. and Shin, G.-J., 2007. Parallel machine scheduling with machine availability and eligibility constraints. European Journal ofOperational Research, 184 (2), 458-467.
    • (2007) European Journal ofOperational Research , vol.184 , Issue.2 , pp. 458-467
    • Liao, L.-W.1    Shin, G.-J.2
  • 16
    • 74549113735 scopus 로고    scopus 로고
    • European Journal ofOperational Research, 156 (1), 261-266.
    • European Journal ofOperational Research, 156 (1), 261-266.
  • 18
    • 0030196914 scopus 로고    scopus 로고
    • Modeling and solving the spatial block scheduling problem in a shipbuilding company
    • Park, K., et al., 1996. Modeling and solving the spatial block scheduling problem in a shipbuilding company. Computer and Industrial Engineering, 30 (3), 357-364.
    • (1996) Computer and Industrial Engineering , vol.30 , Issue.3 , pp. 357-364
    • Park, K.1
  • 20
    • 33750189214 scopus 로고    scopus 로고
    • Approximation bounds for a general class of precedence constrained parallel machine scheduling problems
    • Queyranne, M. and Schulz, A.S., 2006. Approximation bounds for a general class of precedence constrained parallel machine scheduling problems. SIAM Journal on Computing, 35 (5), 1241-1253.
    • (2006) SIAM Journal on Computing , vol.35 , Issue.5 , pp. 1241-1253
    • Queyranne, M.1    Schulz, A.S.2
  • 21
    • 33644537918 scopus 로고    scopus 로고
    • Sequencing precedence-related jobs on two machines to minimize the weighted completion time
    • Ramachandra, G. and Elmaghraby, S.E., 2006. Sequencing precedence-related jobs on two machines to minimize the weighted completion time. International Journal of Production Economics, 100 (1), 44-58.
    • (2006) International Journal of Production Economics , vol.100 , Issue.1 , pp. 44-58
    • Ramachandra, G.1    Elmaghraby, S.E.2
  • 22
    • 33748711826 scopus 로고    scopus 로고
    • Shipbuilding erection network optimization: A TSP method
    • Ranjan, V. and Duck, Y.Y., 2006. Shipbuilding erection network optimization: a TSP method. Journal of Ship Production, 22 (3), 139-146.
    • (2006) Journal of Ship Production , vol.22 , Issue.3 , pp. 139-146
    • Ranjan, V.1    Duck, Y.Y.2
  • 23
    • 34548386186 scopus 로고    scopus 로고
    • Generation of production material information for a building block and simulation of block erection for process planning and scheduling in shipbuilding
    • Roh, M.-I. and Lee, K.-Y., 2007. Generation of production material information for a building block and simulation of block erection for process planning and scheduling in shipbuilding. International Journal of Production Research, 45 (20), 4653-4683.
    • (2007) International Journal of Production Research , vol.45 , Issue.20 , pp. 4653-4683
    • Roh, M.-I.1    Lee, K.-Y.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.