Volumn 19, Issue 3, 2009, Pages 1698-1701
|
Phase II of the albany HTS cable project
|
Author keywords
High temperature superconductors; Power cable installation; Power cable joints; Power cable testing; Superconducting cables; Superconducting transmission lines
|
Indexed keywords
CABLE SYSTEMS;
COMMISSIONING TEST;
CRITICAL CURRENT MEASUREMENTS;
DEMONSTRATION PROJECT;
DI-BSCCO;
GRID OPERATION;
HIGH TEMPERATURE SUPERCONDUCTING;
HTS CABLE;
IN-PHASE;
NATIONAL GRID;
PHASE II;
POWER CABLE INSTALLATION;
POWER CABLE JOINTS;
POWER CABLE TESTING;
POWER GRIDS;
SUPERCONDUCTING TRANSMISSION LINES;
UTILITY NETWORK;
WITHSTAND VOLTAGE;
YBCO COATED CONDUCTORS;
CABLE JOINTING;
CRITICAL CURRENT DENSITY (SUPERCONDUCTIVITY);
CRYOSTATS;
ELECTRIC BATTERIES;
ELECTRIC CURRENT MEASUREMENT;
ELECTRIC LINES;
ELECTRIC POTENTIAL;
ELECTRIC POWER DISTRIBUTION;
ELECTRIC SUBSTATIONS;
ELECTRIC UTILITIES;
HIGH TEMPERATURE SUPERCONDUCTORS;
LIGHT TRANSMISSION;
METRIC SYSTEM;
POWER GENERATION;
SUPERCONDUCTING CABLES;
SUPERCONDUCTIVITY;
TELECOMMUNICATION CABLES;
TRANSMISSION LINE THEORY;
YTTRIUM BARIUM COPPER OXIDES;
CABLES;
|
EID: 68649091681
PISSN: 10518223
EISSN: None
Source Type: Journal
DOI: 10.1109/TASC.2009.2017865 Document Type: Conference Paper |
Times cited : (79)
|
References (6)
|