Volumn 22, Issue 8, 2004, Pages 633-643

Identifying and assessing the critical risk factors in an underground rail project in Thailand: A factor analysis approach

Author keywords

Factor analysis; Importance index; Mass rapid transit project; Risk factors

Indexed keywords

RELIABILITY; RESEARCH AND DEVELOPMENT MANAGEMENT; RISK MANAGEMENT; SOCIETIES AND INSTITUTIONS;

EID: 5444257339     PISSN: 02637863     EISSN: None     Source Type: Journal    
DOI: 10.1016/j.ijproman.2004.05.004     Document Type: Article
Times cited : (186)

References (46)
  • 1
    • 5444256685 scopus 로고    scopus 로고
    • Universal Risk Project Final Report February 2002. Available from Accessed on 14 May 2003
    • Hall D, Hulett D, Universal Risk Project Final Report, February 2002. Available from http://www.risksig.com/articles/ UR%20Project%20Report.doc 2002; Accessed on 14 May 2003
    • (2002)
    • Hall, D.1    Hulett, D.2
  • 2
    • 0242494583 scopus 로고    scopus 로고
    • Developing a risk management matrix for effective project planning - An empirical study
    • Datta S. Mukherjee S.K. Developing a risk management matrix for effective project planning - an empirical study Project Manag. J. 32 2 2001 45-57
    • (2001) Project Manag. J. , vol.32 , Issue.2 , pp. 45-57
    • Datta, S.1    Mukherjee, S.K.2
  • 3
    • 5444255441 scopus 로고    scopus 로고
    • Claims avoidance technique: Best practices for contract administration
    • Harmon KMJ, Stephan BM. Claims avoidance technique: best practices for contract administration. AACE Int. Trans. 2001:CD11-16
    • (2001) AACE Int. Trans.
    • Harmon, K.M.J.1    Stephan, B.M.2
  • 8
    • 0033150275 scopus 로고    scopus 로고
    • Process re-engineering for effective implementation of projects
    • Dey P.K. Process re-engineering for effective implementation of projects Int. J. Project Manag. 17 3 1999 147-159
    • (1999) Int. J. Project Manag. , vol.17 , Issue.3 , pp. 147-159
    • Dey, P.K.1
  • 9
    • 0036539272 scopus 로고    scopus 로고
    • Risk analysis: A subjective process
    • Redmill F. Risk analysis: a subjective process Eng. Manag. J. 12 2 2002 91-96
    • (2002) Eng. Manag. J. , vol.12 , Issue.2 , pp. 91-96
    • Redmill, F.1
  • 10
    • 0031109413 scopus 로고    scopus 로고
    • Project risk management in Hong Kong
    • Shen Y.L. Project risk management in Hong Kong Int. J. Project Manag. 15 2 1997 101-105
    • (1997) Int. J. Project Manag. , vol.15 , Issue.2 , pp. 101-105
    • Shen, Y.L.1
  • 12
    • 5444253073 scopus 로고    scopus 로고
    • An analysis of risk classifications for residential mortgage loans
    • Lui D.Y. Lee S.P. An analysis of risk classifications for residential mortgage loans J. Property Finance 8 3 1997 207-225
    • (1997) J. Property Finance , vol.8 , Issue.3 , pp. 207-225
    • Lui, D.Y.1    Lee, S.P.2
  • 13
    • 0000057558 scopus 로고    scopus 로고
    • Measuring organizational downside risk
    • Miller K.D. Reuer J.J. Measuring organizational downside risk Strat. Manag. J. 17 9 1996 671-691
    • (1996) Strat. Manag. J. , vol.17 , Issue.9 , pp. 671-691
    • Miller, K.D.1    Reuer, J.J.2
  • 14
    • 0002405793 scopus 로고    scopus 로고
    • Organizational characteristics influencing the use of risk analysis in strategic capital investment
    • Ho S.S.M. Pike R.H. Organizational characteristics influencing the use of risk analysis in strategic capital investment Eng. Econom. 43 3 1998 247-268
    • (1998) Eng. Econom. , vol.43 , Issue.3 , pp. 247-268
    • Ho, S.S.M.1    Pike, R.H.2
  • 15
    • 0031705846 scopus 로고    scopus 로고
    • Factors affecting contractors' risk of cost overburden
    • Akinci B. Fischer M. Factors affecting contractors' risk of cost overburden J. Manag. Eng. 14 1 1998 67-76
    • (1998) J. Manag. Eng. , vol.14 , Issue.1 , pp. 67-76
    • Akinci, B.1    Fischer, M.2
  • 16
    • 0141988807 scopus 로고    scopus 로고
    • Design documents quality in the japanese construction industry: Factors influencing and impacts on construction process
    • Andi S. Minato T. Design documents quality in the japanese construction industry: factors influencing and impacts on construction process Int. J. Project Manag. 21 7 2003 537-546
    • (2003) Int. J. Project Manag. , vol.21 , Issue.7 , pp. 537-546
    • Andi, S.1    Minato, T.2
  • 17
    • 0037402597 scopus 로고    scopus 로고
    • Modeling global risk factors affecting construction cost performance
    • Baloi D. Price A.D.F. Modeling global risk factors affecting construction cost performance Int. J. Project Manag. 21 4 2003 261-269
    • (2003) Int. J. Project Manag. , vol.21 , Issue.4 , pp. 261-269
    • Baloi, D.1    Price, A.D.F.2
  • 19
    • 0031078243 scopus 로고    scopus 로고
    • A comparative study of causes of time overruns in Hong Kong construction projects
    • Chan D.W.M. Kumaraswamy M.M. A comparative study of causes of time overruns in Hong Kong construction projects Int. J. Project Manag. 15 1 1997 55-63
    • (1997) Int. J. Project Manag. , vol.15 , Issue.1 , pp. 55-63
    • Chan, D.W.M.1    Kumaraswamy, M.M.2
  • 20
    • 0344267707 scopus 로고    scopus 로고
    • Contractual risk and liability sharing in hydropower construction
    • Charoenngam C. Yeh C.Y. Contractual risk and liability sharing in hydropower construction Int. J. Project Manag. 17 1 1999 29-37
    • (1999) Int. J. Project Manag. , vol.17 , Issue.1 , pp. 29-37
    • Charoenngam, C.1    Yeh, C.Y.2
  • 21
    • 0032332292 scopus 로고    scopus 로고
    • ConSERV, a project specific risk management concept
    • Conroy G. Soltan H. ConSERV, a project specific risk management concept Int. J. Project Manag. 16 6 1998 353-366
    • (1998) Int. J. Project Manag. , vol.16 , Issue.6 , pp. 353-366
    • Conroy, G.1    Soltan, H.2
  • 22
    • 0001848701 scopus 로고
    • Planning for project control through risk analysis: A petroleum pipeline-laying project
    • Dey P. Tabucanon M.T. Ogunlana S.O. Planning for project control through risk analysis: a petroleum pipeline-laying project Int. J. Project Manag. 12 1 1994 23-33
    • (1994) Int. J. Project Manag. , vol.12 , Issue.1 , pp. 23-33
    • Dey, P.1    Tabucanon, M.T.2    Ogunlana, S.O.3
  • 23
    • 0035426616 scopus 로고    scopus 로고
    • Risk and its management in the Kuwaiti construction industry: A contractors' perspective
    • Kartam N.A. Kartam S.A. Risk and its management in the Kuwaiti construction industry: a contractors' perspective Int. J. Project Manag. 19 6 2001 325-335
    • (2001) Int. J. Project Manag. , vol.19 , Issue.6 , pp. 325-335
    • Kartam, N.A.1    Kartam, S.A.2
  • 24
    • 0002733516 scopus 로고
    • Construction time - Influencing factors: The contractor' perspective
    • Nkado R. Construction time - influencing factors: the contractor' perspective Construct. Manag. Econom. 13 1995 81-89
    • (1995) Construct. Manag. Econom. , vol.13 , pp. 81-89
    • Nkado, R.1
  • 25
  • 26
    • 0033177429 scopus 로고    scopus 로고
    • Applying a risk management process (RMP) to manage cost risk for an EHV transmission line project
    • Tummala V.M.R. Burchett J.F. Applying a risk management process (RMP) to manage cost risk for an EHV transmission line project Int. J. Project Manag. 17 4 1999 223-235
    • (1999) Int. J. Project Manag. , vol.17 , Issue.4 , pp. 223-235
    • Tummala, V.M.R.1    Burchett, J.F.2
  • 27
    • 0242314515 scopus 로고    scopus 로고
    • Construction total project management planning issues
    • Yates J.K. Eskander A. Construction total project management planning issues J. Manag. Eng. 33 1 2002 37-48
    • (2002) J. Manag. Eng. , vol.33 , Issue.1 , pp. 37-48
    • Yates, J.K.1    Eskander, A.2
  • 28
    • 0011127465 scopus 로고
    • Risk management for overseas construction projects
    • Zhi H. Risk management for overseas construction projects Int. J. Project Manag. 13 4 1995 231-237
    • (1995) Int. J. Project Manag. , vol.13 , Issue.4 , pp. 231-237
    • Zhi, H.1
  • 32
    • 0003425438 scopus 로고
    • Factor analysis: Statistical methods and practical issues. Sage university paper series on quantitative applications in the social sciences
    • Newbury Park: Sage Publication
    • Kim JO, Mueller CW. Factor analysis: statistical methods and practical issues. Sage university paper series on quantitative applications in the social sciences, Newbury Park: Sage Publication; 1978
    • (1978)
    • Kim, J.O.1    Mueller, C.W.2
  • 38
    • 0002519970 scopus 로고
    • A study of measuring the critical factors of quality management
    • Badri M. Davis D. Davis D. A study of measuring the critical factors of quality management Int. J. Qual. Reliab. Manag. 12 2 1995 36-53
    • (1995) Int. J. Qual. Reliab. Manag. , vol.12 , Issue.2 , pp. 36-53
    • Badri, M.1    Davis, D.2    Davis, D.3
  • 39
    • 0442279108 scopus 로고    scopus 로고
    • Critical success factors in small and medium enterprises: Survey results
    • Yusof S.M. Aspinwall E.M. Critical success factors in small and medium enterprises: survey results Total Qual. Manag. 11 4 2000 S448-S462
    • (2000) Total Qual. Manag. , vol.11 , Issue.4
    • Yusof, S.M.1    Aspinwall, E.M.2
  • 40
    • 0000009769 scopus 로고
    • Evaluating structural equation models with unobservable variable and measurement error
    • Fornell C. Larcker D.F. Evaluating structural equation models with unobservable variable and measurement error J. Market. Res. 17 1981 39-50
    • (1981) J. Market. Res. , vol.17 , pp. 39-50
    • Fornell, C.1    Larcker, D.F.2
  • 41
    • 0742319505 scopus 로고
    • Caution in the use of difference scores in consumer research
    • Peter P.J. Churchill G.A. Brown T.J. Caution in the use of difference scores in consumer research J. Consumer Res. 19 4 1993 655-662
    • (1993) J. Consumer Res. , vol.19 , Issue.4 , pp. 655-662
    • Peter, P.J.1    Churchill, G.A.2    Brown, T.J.3
  • 42
    • 84986065113 scopus 로고    scopus 로고
    • Identifying key factors affecting consumer purchase behavior in an online shopping context
    • Park C.H. Kim Y.G. Identifying key factors affecting consumer purchase behavior in an online shopping context Int. J. Retail Distrib. Manag. 31 1 2003 16-29
    • (2003) Int. J. Retail Distrib. Manag. , vol.31 , Issue.1 , pp. 16-29
    • Park, C.H.1    Kim, Y.G.2
  • 43
    • 0003668648 scopus 로고
    • A primer of LISREL. Basic applications and programming for confirmatory factor analytic models
    • New York, NY: Spring-Verlag
    • Byrne B.M. A primer of LISREL. Basic applications and programming for confirmatory factor analytic models 1989 Spring-Verlag New York, NY
    • (1989)
    • Byrne, B.M.1
  • 44
    • 0000153880 scopus 로고
    • Multitrait-multimethod matrices in consumer research
    • Bagozzi R.P. Yi Y. Multitrait-multimethod matrices in consumer research J. Consumer Res. 17 1991 426-439
    • (1991) J. Consumer Res. , vol.17 , pp. 426-439
    • Bagozzi, R.P.1    Yi, Y.2
  • 45
    • 0000643379 scopus 로고
    • Factors considered in tendering decisions by top UK contractors
    • Shash A.A. Factors considered in tendering decisions by top UK contractors Construct. Manag. Econom. 11 2 1993 111-118
    • (1993) Construct. Manag. Econom. , vol.11 , Issue.2 , pp. 111-118
    • Shash, A.A.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.