메뉴 건너뛰기




Volumn 23, Issue 3, 2008, Pages 1115-1124

An MILP approach for short-term hydro scheduling and unit commitment with head-dependent reservoir

Author keywords

Hydro power plants operation; Hydro reservoir management; Mixed integer linear programming; Unit commitment

Indexed keywords

CHLORINE COMPOUNDS; COMPUTER SOFTWARE; ELECTRIC LOAD FORECASTING; ELECTRIC POWER GENERATION; HYDROELECTRIC POWER; INTEGER PROGRAMMING; LINEAR PROGRAMMING; LINEARIZATION; POWER GENERATION; SCHEDULING; UNMANNED AERIAL VEHICLES (UAV);

EID: 49249094152     PISSN: 08858950     EISSN: None     Source Type: Journal    
DOI: 10.1109/TPWRS.2008.926704     Document Type: Article
Times cited : (306)

References (16)
  • 1
    • 2542598480 scopus 로고    scopus 로고
    • Unit commitment - A bibliographical survey
    • May
    • N. Padhy, "Unit commitment - A bibliographical survey," IEEE Trans. Power Syst., vol. 19, no. 2, pp. 1196-1205, May 2004.
    • (2004) IEEE Trans. Power Syst , vol.19 , Issue.2 , pp. 1196-1205
    • Padhy, N.1
  • 2
    • 0028428070 scopus 로고
    • Optimal short-term scheduling for a large-scale cascaded hydro system
    • May
    • M. Piekutowki, T. Litwinowcz, and R. Frowd, "Optimal short-term scheduling for a large-scale cascaded hydro system," IEEE Trans. Power Syst., vol. 9, no. 2, pp. 805-811, May 1994.
    • (1994) IEEE Trans. Power Syst , vol.9 , Issue.2 , pp. 805-811
    • Piekutowki, M.1    Litwinowcz, T.2    Frowd, R.3
  • 3
    • 33244473987 scopus 로고    scopus 로고
    • Parameterisation effect on the behaviour of a head-dependent hydro chain using a nonlinear model
    • J. Catalão, S. Mariano, V. Mendes, and L. Ferreira, "Parameterisation effect on the behaviour of a head-dependent hydro chain using a nonlinear model," Elect. Power Syst. Res., vol. 76, pp. 404-412, 2006.
    • (2006) Elect. Power Syst. Res , vol.76 , pp. 404-412
    • Catalão, J.1    Mariano, S.2    Mendes, V.3    Ferreira, L.4
  • 4
    • 0037291589 scopus 로고    scopus 로고
    • Fast evolutionary programming techniques for short-term hydrothermal scheduling
    • Feb
    • N. Sinha, R. Chakrabarti, and P. Chattopadhyay, "Fast evolutionary programming techniques for short-term hydrothermal scheduling," IEEE Trans. Power Syst., vol. 18, no. 1, pp. 214-220, Feb. 2003.
    • (2003) IEEE Trans. Power Syst , vol.18 , Issue.1 , pp. 214-220
    • Sinha, N.1    Chakrabarti, R.2    Chattopadhyay, P.3
  • 5
    • 0032073503 scopus 로고    scopus 로고
    • A genetic algorithm modelling framework and solution technique for short term optimal hydrothermal scheduling
    • May
    • S. Orero and M. Irving, "A genetic algorithm modelling framework and solution technique for short term optimal hydrothermal scheduling," IEEE Trans. Power Syst., vol. 13, no. 2, pp. 501-518, May 1998.
    • (1998) IEEE Trans. Power Syst , vol.13 , Issue.2 , pp. 501-518
    • Orero, S.1    Irving, M.2
  • 6
    • 2542593940 scopus 로고    scopus 로고
    • Pumped-storage hydro-turbine bidding strategies in a competitive electricity market
    • May
    • N. Lu, J. Chow, and A. Desrochers, "Pumped-storage hydro-turbine bidding strategies in a competitive electricity market," IEEE Trans. Power Syst., vol. 19, no. 2, pp. 834-841, May 2004.
    • (2004) IEEE Trans. Power Syst , vol.19 , Issue.2 , pp. 834-841
    • Lu, N.1    Chow, J.2    Desrochers, A.3
  • 7
    • 81755177923 scopus 로고    scopus 로고
    • Solving the unit commitment problem of hydropower plants via Lagrangian relaxation and sequential quadratic programming
    • E. Finardi, E. Da Silva, and C. Sagastizabal, "Solving the unit commitment problem of hydropower plants via Lagrangian relaxation and sequential quadratic programming," Comput. Appl. Math., vol. 24, no. 3, pp. 317-341, 2005.
    • (2005) Comput. Appl. Math , vol.24 , Issue.3 , pp. 317-341
    • Finardi, E.1    Da Silva, E.2    Sagastizabal, C.3
  • 8
    • 85026387283 scopus 로고    scopus 로고
    • A mixed integer linear programming based hydro unit commitment
    • Jul. 18-22
    • C. Chang and J. Waight, "A mixed integer linear programming based hydro unit commitment," in Proc. Power Eng. Soc. Summer Meeting, Jul. 18-22, 1999.
    • (1999) Proc. Power Eng. Soc. Summer Meeting
    • Chang, C.1    Waight, J.2
  • 9
    • 0035507082 scopus 로고    scopus 로고
    • Experiences with mixed integer linear programming based approaches on short-term hydro scheduling
    • Nov
    • G. Chang, M. Aganagic, J. Waight, J. Medina, T. Burton, S. Reeves, and M. Christoforidis, "Experiences with mixed integer linear programming based approaches on short-term hydro scheduling," IEEE Trans. Power Syst., vol. 16, no. 4, pp. 743-749, Nov. 2001.
    • (2001) IEEE Trans. Power Syst , vol.16 , Issue.4 , pp. 743-749
    • Chang, G.1    Aganagic, M.2    Waight, J.3    Medina, J.4    Burton, T.5    Reeves, S.6    Christoforidis, M.7
  • 11
    • 34250337602 scopus 로고    scopus 로고
    • Short-term hydro scheduling with cascaded and head-dependent reservoirs based on mixed-integer linear programming
    • Sep. 10-13
    • J. García-González and G. Castro, "Short-term hydro scheduling with cascaded and head-dependent reservoirs based on mixed-integer linear programming," in IEEE Porto Power Tech, Sep. 10-13, 2001.
    • (2001) IEEE Porto Power Tech
    • García-González, J.1    Castro, G.2
  • 12
    • 33947674280 scopus 로고    scopus 로고
    • Risk-averse profit-based optimal scheduling of a hydro-chain in the day-ahead electricity market
    • J. García-González, E. Parrilla, and A. Mateo, "Risk-averse profit-based optimal scheduling of a hydro-chain in the day-ahead electricity market," Eur. J. Oper. Res., vol. 181, no. 3, pp. 1354-1369, 2007.
    • (2007) Eur. J. Oper. Res , vol.181 , Issue.3 , pp. 1354-1369
    • García-González, J.1    Parrilla, E.2    Mateo, A.3
  • 13
    • 0036872146 scopus 로고    scopus 로고
    • Self-scheduling of a hydro producer in a pool-based electricity market
    • Nov
    • A. Conejo, J. Arroyo, J. Contreras, and F. Villamor, "Self-scheduling of a hydro producer in a pool-based electricity market," IEEE Trans. Power Syst., vol. 17, no. 4, pp. 1265-1272, Nov. 2002.
    • (2002) IEEE Trans. Power Syst , vol.17 , Issue.4 , pp. 1265-1272
    • Conejo, A.1    Arroyo, J.2    Contreras, J.3    Villamor, F.4
  • 14
    • 0012024683 scopus 로고    scopus 로고
    • Online, Available
    • Ilog CPLEX. [Online]. Available: http://www.ilog.com/products/cplex.
    • Ilog CPLEX
  • 15
    • 33747623533 scopus 로고    scopus 로고
    • A computationally efficient mixed-integer linear formulation for the thermal unit commitment problem
    • Aug
    • M. Carrión and J. M. Arroyo, "A computationally efficient mixed-integer linear formulation for the thermal unit commitment problem," IEEE Trans. Power Syst., vol. 21, no. 3, pp. 1371-1378, Aug. 2006.
    • (2006) IEEE Trans. Power Syst , vol.21 , Issue.3 , pp. 1371-1378
    • Carrión, M.1    Arroyo, J.M.2
  • 16
    • 0142029542 scopus 로고    scopus 로고
    • Models for representing piecewise linear cost functions
    • A. Keha, I. de Farias, and G. Nemhauser, "Models for representing piecewise linear cost functions," Oper. Res. Lett., vol. 32, pp. 44-48, 2004.
    • (2004) Oper. Res. Lett , vol.32 , pp. 44-48
    • Keha, A.1    de Farias, I.2    Nemhauser, G.3


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.