메뉴 건너뛰기




Volumn 22, Issue 3, 2007, Pages 1250-1258

Vulnerability of large steam turbine generators to torsional interactions during electrical grid disturbances

Author keywords

Shaft fatigue; SSR; Torsional interaction

Indexed keywords

ELECTRIC POWER PLANTS; FATIGUE OF MATERIALS; ROTORS; TORQUE; TORSIONAL STRESS; TURBOGENERATORS;

EID: 34548050717     PISSN: 08858950     EISSN: None     Source Type: Journal    
DOI: 10.1109/TPWRS.2007.901755     Document Type: Article
Times cited : (20)

References (20)
  • 2
    • 0018014792 scopus 로고
    • Torsional fatigue of turbine-generator shafts caused by different electrical system faults and switching operations
    • Sep./Oct
    • J. S. Joyce, T. Kulig, and D. Lambrecht, "Torsional fatigue of turbine-generator shafts caused by different electrical system faults and switching operations," IEEE Trans. Power App. Syst., vol. PAS-97, no. 5, pp. 1965-1973, Sep./Oct. 1978.
    • (1978) IEEE Trans. Power App. Syst , vol.PAS-97 , Issue.5 , pp. 1965-1973
    • Joyce, J.S.1    Kulig, T.2    Lambrecht, D.3
  • 3
    • 0018442940 scopus 로고
    • Network alternatives to reduce turbine-generator shaft stresses
    • Mar./Apr
    • P. A. E. Rusche, "Network alternatives to reduce turbine-generator shaft stresses," IEEE Trans. Power App. Syst., vol. PAS-98, no. 2, pp. 408-413, Mar./Apr. 1979.
    • (1979) IEEE Trans. Power App. Syst , vol.PAS-98 , Issue.2 , pp. 408-413
    • Rusche, P.A.E.1
  • 4
    • 0018915794 scopus 로고
    • Status of evaluating the fatigue of large steam turbine-generator caused by electrical disturbances
    • Jan./Feb
    • J. S. Joyce and D. Lambrecht, "Status of evaluating the fatigue of large steam turbine-generator caused by electrical disturbances," IEEE Trans. Power App. Syst., vol. PAS-99, no. 1, pp. 111-119, Jan./Feb. 1980.
    • (1980) IEEE Trans. Power App. Syst , vol.PAS-99 , Issue.1 , pp. 111-119
    • Joyce, J.S.1    Lambrecht, D.2
  • 5
    • 0018919269 scopus 로고
    • Important parameters in considering transient torques on turbine-generator shaft systems
    • Jan./Feb
    • D. G. Ramey, A. C. Sismour, and G. C. Kung, "Important parameters in considering transient torques on turbine-generator shaft systems," IEEE Trans. Power App. Syst., vol. PAS-99, no. 1, pp. 311-317, Jan./Feb. 1980.
    • (1980) IEEE Trans. Power App. Syst , vol.PAS-99 , Issue.1 , pp. 311-317
    • Ramey, D.G.1    Sismour, A.C.2    Kung, G.C.3
  • 6
    • 0019043010 scopus 로고
    • Stressing of large turbine-generators at shaft couplings and LP turbine final-stage blade roots following clearance of grid system faults and faulty synchronisation
    • Jul./Aug
    • T. J. Hammons, "Stressing of large turbine-generators at shaft couplings and LP turbine final-stage blade roots following clearance of grid system faults and faulty synchronisation," IEEE Trans. Power App. Syst., vol. PAS-99, no. 4, pp. 1652-1662, Jul./Aug. 1980.
    • (1980) IEEE Trans. Power App. Syst , vol.PAS-99 , Issue.4 , pp. 1652-1662
    • Hammons, T.J.1
  • 7
    • 0019080382 scopus 로고
    • Turbine-generator shaft stresses due to network disturbances: A bibliography with abstracts
    • Nov./Dec
    • P. A. Rusche, "Turbine-generator shaft stresses due to network disturbances: A bibliography with abstracts," IEEE Trans. Power App. Syst., vol. PAS-99, no. 6, pp. 2146-2152, Nov./Dec. 1980.
    • (1980) IEEE Trans. Power App. Syst , vol.PAS-99 , Issue.6 , pp. 2146-2152
    • Rusche, P.A.1
  • 8
    • 0019063837 scopus 로고
    • Evaluation of the effect of power circuit breaker reclosing practices on turbine-generator shafts
    • Sep./Oct
    • C. E. J. Bowler, P. G. Brown, and D. N. Walker, "Evaluation of the effect of power circuit breaker reclosing practices on turbine-generator shafts," IEEE Trans. Power App. Syst., vol. PAS-99, no. 5, pp. 1764-1779, Sep./Oct. 1980.
    • (1980) IEEE Trans. Power App. Syst , vol.PAS-99 , Issue.5 , pp. 1764-1779
    • Bowler, C.E.J.1    Brown, P.G.2    Walker, D.N.3
  • 9
    • 0019060502 scopus 로고
    • Shaft torsional stress due to asynchronous faulty synchronization
    • Sep./Oct
    • J. V. Mitsche and P. A. Rusche, "Shaft torsional stress due to asynchronous faulty synchronization," IEEE Trans. Power App. Syst. vol. PAS-99, no. 5, pp. 1 864-1 870, Sep./Oct. 1980.
    • (1980) IEEE Trans. Power App. Syst , vol.PAS-99 , Issue.5
    • Mitsche, J.V.1    Rusche, P.A.2
  • 11
    • 34548015367 scopus 로고    scopus 로고
    • Torsional Interaction Between Electrical Network Phenomena and Turbine-Generator Shafts: Plant Vulnerability, EPRI Tech
    • Rep. 1013460, Nov
    • Torsional Interaction Between Electrical Network Phenomena and Turbine-Generator Shafts: Plant Vulnerability, EPRI Tech. Rep. 1013460, Nov. 2006.
    • (2006)
  • 12
    • 34548011392 scopus 로고    scopus 로고
    • Determination of Torsional Fatigue Life of Large Turbine Generator Shafts, EPRI rep. EL-3083, 1984.
    • Determination of Torsional Fatigue Life of Large Turbine Generator Shafts, EPRI rep. EL-3083, 1984.
  • 13
    • 34548042471 scopus 로고    scopus 로고
    • A Methodology for Predicting Fatigue Life of Turbine-Generator Shafts, EPRI rep. EL 4333, 1985.
    • A Methodology for Predicting Fatigue Life of Turbine-Generator Shafts, EPRI rep. EL 4333, 1985.
  • 14
    • 34548032512 scopus 로고    scopus 로고
    • Standard for Cylindrical-Rotor 50 and 60 Hz, Synchronous Generators Rated 10 MVA and Above, IEEE Std. 50.13.
    • Standard for Cylindrical-Rotor 50 and 60 Hz, Synchronous Generators Rated 10 MVA and Above, IEEE Std. 50.13.
  • 15
    • 34548042228 scopus 로고    scopus 로고
    • P. M. Anderson and R. G. Farmer, Series Compensation of Power Systems Encinitas, CA: PBLSH!, 1996.
    • P. M. Anderson and R. G. Farmer, Series Compensation of Power Systems Encinitas, CA: PBLSH!, 1996.
  • 16
    • 0019040551 scopus 로고
    • IEEE Screening Guide For Planned Steady-State Switching Operations to Minimize Harmful Effects on Steam Turbine-Generators
    • IEEE Working Group Report, Jul./Aug
    • IEEE Working Group Report, "IEEE Screening Guide For Planned Steady-State Switching Operations to Minimize Harmful Effects on Steam Turbine-Generators," IEEE Trans. Power App. Syst., vol. PAS-99, no. 4, pp. 1519-1521, Jul./Aug. 1980.
    • (1980) IEEE Trans. Power App. Syst , vol.PAS-99 , Issue.4 , pp. 1519-1521
  • 19
    • 0022029418 scopus 로고
    • Analysis of thyristor-controlled shunt SSR countermeasures
    • Mar
    • N. C. Abi-Samra, R. F. Smith, and T. E. McDermott, "Analysis of thyristor-controlled shunt SSR countermeasures," IEEE Trans. Power App. Syst., vol. PAS-104, no. 3, pp. 583-597, Mar. 1985.
    • (1985) IEEE Trans. Power App. Syst , vol.PAS-104 , Issue.3 , pp. 583-597
    • Abi-Samra, N.C.1    Smith, R.F.2    McDermott, T.E.3
  • 20
    • 0017536440 scopus 로고
    • First benchmark model for computer simulation of subsynchronous resonance
    • IEEE SSR Task Force
    • IEEE SSR Task Force, "First benchmark model for computer simulation of subsynchronous resonance," IEEE Trans. Power App. Syst., vol. PAS-96, no. 5, pp. 1565-1570, 1977.
    • (1977) IEEE Trans. Power App. Syst , vol.PAS-96 , Issue.5 , pp. 1565-1570


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.