Volumn 131, Issue 9, 2005, Pages 963-972

Financial risk analysis of project finance in Indonesian toll roads

Author keywords

Build operate transfer; Construction industry; Financing; Indonesia; Risk analysis; Simulation; Toll roads

Indexed keywords

COMPUTER SIMULATION; FINANCE; PROJECT MANAGEMENT; REGULATORY COMPLIANCE; RISK ASSESSMENT; TOLL HIGHWAYS;

EID: 24944490978     PISSN: 07339364     EISSN: None     Source Type: Journal    
DOI: 10.1061/(ASCE)0733-9364(2005)131:9(963)     Document Type: Article
Times cited : (55)

References (27)
  • 7
    • 0029539141 scopus 로고
    • Risk analysis of a build-operate-transfer (BOT) power plant project
    • IEEE, New York
    • Chee, T. S., and Yeo, K. T. (1995). "Risk analysis of a build-operate-transfer (BOT) power plant project." Proc., Annual Int. Engineering Management Conf., IEEE, New York, 275-280.
    • (1995) Proc., Annual Int. Engineering Management Conf. , pp. 275-280
    • Chee, T.S.1    Yeo, K.T.2
  • 13
    • 0041639624 scopus 로고    scopus 로고
    • Risk analysis in investment appraisal based on the Monte Carlo simulation technique
    • Hacura, A., Jadamus-Hacura, M., and Kocot, A. (2001). "Risk analysis in investment appraisal based on the Monte Carlo simulation technique." Eur. Phys. J. B 20, 551-553.
    • (2001) Eur. Phys. J. B , vol.20 , pp. 551-553
    • Hacura, A.1    Jadamus-Hacura, M.2    Kocot, A.3
  • 15
    • 0034225021 scopus 로고    scopus 로고
    • Investment risk analysis in airport parking facility development
    • Javid, M., and Seneviratne, P. N. (2000). "Investment risk analysis in airport parking facility development." J. Constr. Eng. Manage., 126(4), 298-305.
    • (2000) J. Constr. Eng. Manage. , vol.126 , Issue.4 , pp. 298-305
    • Javid, M.1    Seneviratne, P.N.2
  • 17
    • 0346223566 scopus 로고
    • Equivalence among alternative portfolio selection criteria
    • H. Levy and M. Sarnat, eds., Academic, New York
    • Kira, D., and Ziemba, W. T. (1977). "Equivalence among alternative portfolio selection criteria." Financial decision making under uncertainty, H. Levy and M. Sarnat, eds., Academic, New York, 151-161.
    • (1977) Financial Decision Making under Uncertainty , pp. 151-161
    • Kira, D.1    Ziemba, W.T.2
  • 18
    • 0031121661 scopus 로고    scopus 로고
    • Appropriate appraisal and apportionment of megaproject risks
    • Kumaraswamy, M. (1997). "Appropriate appraisal and apportionment of megaproject risks." J. Prof. Issues Eng. Educ. Pract., 123(2), 51-56.
    • (1997) J. Prof. Issues Eng. Educ. Pract. , vol.123 , Issue.2 , pp. 51-56
    • Kumaraswamy, M.1
  • 19
    • 0032630817 scopus 로고    scopus 로고
    • Build operate transfer municipal bridge projects in India
    • Malini, E. (1999). "Build operate transfer municipal bridge projects in India." J. Manage. Eng., 15(4), 51-58.
    • (1999) J. Manage. Eng. , vol.15 , Issue.4 , pp. 51-58
    • Malini, E.1
  • 21
    • 0036932439 scopus 로고    scopus 로고
    • An empirical evaluation of sampling methods in risk analysis simulation: Quasi-Monte Carlo, descriptive sampling, and Latin Hypercube sampling
    • IEEE
    • Saliby, E., and Pacheco, F. (2002). "An empirical evaluation of sampling methods in risk analysis simulation: quasi-Monte Carlo, descriptive sampling, and Latin Hypercube sampling." Winter Proc. Simul. Conf., IEEE, Vol. 2, 1606-1610.
    • (2002) Winter Proc. Simul. Conf. , vol.2 , pp. 1606-1610
    • Saliby, E.1    Pacheco, F.2
  • 22
    • 0345371036 scopus 로고
    • Risk analysis in investment appraisal
    • Savvides, S. C. (1994). "Risk analysis in investment appraisal." Econ. Sys. Res., 9(1), 3-18.
    • (1994) Econ. Sys. Res. , vol.9 , Issue.1 , pp. 3-18
    • Savvides, S.C.1
  • 23
    • 0031225023 scopus 로고    scopus 로고
    • Transportation infrastructure financing: Evaluation and alternatives
    • Seneviratne, P. N., and Ranasinghe, M. (1997). "Transportation infrastructure financing: evaluation and alternatives." J. Infrastruct. Syst., 3(3), 111-118.
    • (1997) J. Infrastruct. Syst. , vol.3 , Issue.3 , pp. 111-118
    • Seneviratne, P.N.1    Ranasinghe, M.2
  • 25
    • 24944575872 scopus 로고    scopus 로고
    • Asian toll road development program: Review of recent toll road experience in selected countries and preliminary tool kit for toll road development
    • (1999), Washington, D.C.
    • World Bank and Ministry of Construction Japan. (1999). "Asian toll road development program: review of recent toll road experience in selected countries and preliminary tool kit for toll road development" (1999) Draft Final Rep., Washington, D.C.
    • (1999) Draft Final Rep.
  • 26
    • 0008563034 scopus 로고    scopus 로고
    • NPV-at risk method in infrastructure project investment evaluation
    • Ye, S., and Tiong, R. L. K. (2000). "NPV-at risk method in infrastructure project investment evaluation." J. Constr. Eng. Manage., 126(3), 227-233.
    • (2000) J. Constr. Eng. Manage. , vol.126 , Issue.3 , pp. 227-233
    • Ye, S.1    Tiong, R.L.K.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.