Volumn 4, Issue , 2000, Pages 1975-1980

Challenges for developing nationwide interconnected power systems in China

Author keywords

Interconnected power systems; Interconnections; Power system planning

Indexed keywords

ELECTRIC INDUSTRY; ELECTRIC POWER GENERATION; ELECTRIC POWER TRANSMISSION; ELECTRIC POWER TRANSMISSION NETWORKS; ENERGY RESOURCES; ENERGY UTILIZATION; INDUSTRIAL ECONOMICS; INSTALLATION; MARKETING; PLANNING;

EID: 0037816217     PISSN: None     EISSN: None     Source Type: Conference Proceeding    
DOI: None     Document Type: Conference Paper
Times cited : (2)

References (7)
  • 1
    • 0038241761 scopus 로고    scopus 로고
    • Proposal of a strategic trunk line scheme of inter-regional electric power grid in China
    • February
    • Liu Zhaoxu, "Proposal of a strategic trunk line scheme of inter-regional electric power grid in China", Power System Technology, vol.22 No.2, February 1998
    • (1998) Power System Technology , vol.22 , Issue.2
    • Liu, Z.1
  • 2
    • 0038580513 scopus 로고    scopus 로고
    • To forward China power industry with great opportunity and expectation to 21st century
    • October
    • Gao Yan, "To forward China power industry with great opportunity and expectation to 21st century", Electra No. 180 October 1998
    • (1998) Electra , Issue.180
    • Gao, Y.1
  • 3
    • 0038580518 scopus 로고    scopus 로고
    • Tendency and prospect of national electric power system interconnection in China
    • Lu Jian, "Tendency and prospect of national electric power system interconnection in China", Electricity-CSEE/ vol. 10 No. 1
    • Electricity-CSEE , vol.10 , Issue.1
    • Lu, J.1
  • 4
    • 0038241754 scopus 로고    scopus 로고
    • The development and decision-making of the China's electric power network
    • February
    • Xu Bowen, "The development and decision-making of the China's electric power network", Power System Technology, vol.22 No.2, February 1998
    • (1998) Power System Technology , vol.22 , Issue.2
    • Xu, B.1
  • 5
    • 1842425892 scopus 로고    scopus 로고
    • Technical investigation of the future Chinese interconnected power systems and higher AC voltage(phase 1)
    • June
    • Guo Jianbo, Yao Guocan, Xu Zhengxiong, Yin Yonghua, "Technical investigation of the future Chinese interconnected power systems and Higher AC voltage(phase 1)", Power System Technology, vol.22 No.6, June 1998
    • (1998) Power System Technology , vol.22 , Issue.6
    • Guo, J.1    Yao, G.2    Xu, Z.3    Yin, Y.4
  • 6
    • 0038241753 scopus 로고    scopus 로고
    • Research on nationwide integrated power system and regional trunk network planning
    • January
    • Zheng Meite, "Research on nationwide integrated power system and regional trunk network planning", Power System Technology, vol.23 No.1, January 1999
    • (1999) Power System Technology , vol.23 , Issue.1
    • Zheng, M.1
  • 7
    • 0037566204 scopus 로고    scopus 로고
    • Planning study on national power grid interconnection centered on three Gorge hydropower station
    • Zhou Xiaoqian, "Planning study on national power grid interconnection centered on Three Gorge hydropower station", Electricity-CSEE/ vol. 10 No. 2, 1999
    • (1999) Electricity-CSEE , vol.10 , Issue.2
    • Zhou, X.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.