메뉴 건너뛰기




Volumn 4, Issue 2, 1999, Pages 56-63

Microtunneling technology for conduit construction

Author keywords

[No Author keywords available]

Indexed keywords

ACCIDENT PREVENTION; ECONOMIC AND SOCIAL EFFECTS; ENVIRONMENTAL IMPACT; OCCUPATIONAL RISKS; PERSONNEL; PRODUCTIVITY; REMOTE CONTROL; TRENCHING; TUNNELING MACHINES; UNDERGROUND STRUCTURES;

EID: 0033130742     PISSN: 10840680     EISSN: None     Source Type: Journal    
DOI: 10.1061/(ASCE)1084-0680(1999)4:2(56)     Document Type: Article
Times cited : (9)

References (19)
  • 1
    • 0029412610 scopus 로고
    • Minidirectional drilling for installation of underground conduit
    • Barras, G. C., and Mayo, R. E. (1995). "Minidirectional drilling for installation of underground conduit." J. Constr. Engrg. and Mgmt., ASCE, 121(4), 364-369.
    • (1995) J. Constr. Engrg. and Mgmt., ASCE , vol.121 , Issue.4 , pp. 364-369
    • Barras, G.C.1    Mayo, R.E.2
  • 2
    • 0007843803 scopus 로고
    • Trends and prospects of microtunneling in the Federal Republic of Germany
    • Balkema, Rotterdam, The Netherlands
    • Beyert, J. (1992). "Trends and prospects of microtunneling in the Federal Republic of Germany." Microtunneling, Balkema, Rotterdam, The Netherlands, 5-7.
    • (1992) Microtunneling , pp. 5-7
    • Beyert, J.1
  • 3
    • 0345349415 scopus 로고
    • What is trenchless technology anyway
    • Boyce, G. M. (1994). "What is trenchless technology anyway." Trenchless Technol., 5(6), 13.
    • (1994) Trenchless Technol. , vol.5 , Issue.6 , pp. 13
    • Boyce, G.M.1
  • 4
    • 0026981594 scopus 로고
    • Manholes and microtunneling
    • Cruz, E. Jr. (1992). "Manholes and microtunneling." Civ. Engrg., ASCE, 62(12), 52-55.
    • (1992) Civ. Engrg., ASCE , vol.62 , Issue.12 , pp. 52-55
    • Cruz E., Jr.1
  • 5
    • 0007791658 scopus 로고
    • Transmission main constructed with microtunneling techniques
    • Haynes, C., Proffit, H. K., and Brown, J. T. (1995). "Transmission main constructed with microtunneling techniques." No-Dig Engrg., Trenchless Technol., 2(2), 18-23.
    • (1995) No-dig Engrg., Trenchless Technol. , vol.2 , Issue.2 , pp. 18-23
    • Haynes, C.1    Proffit, H.K.2    Brown, J.T.3
  • 6
    • 4243689659 scopus 로고
    • Microtunneling: Poised for major growth
    • June 12
    • Iseley, D. T., and Brown, D. (1995). "Microtunneling: Poised for major growth." ENR, June 12, U4-U11.
    • (1995) ENR
    • Iseley, D.T.1    Brown, D.2
  • 7
    • 0344487033 scopus 로고
    • Microtunneling forges ahead
    • Aug. 17
    • Kosowatz, J. J., and Powers, M. (1992). "Microtunneling forges ahead." ENR, Aug. 17, 32-36.
    • (1992) ENR , pp. 32-36
    • Kosowatz, J.J.1    Powers, M.2
  • 8
    • 0026986768 scopus 로고
    • Underground research: Here and there
    • Sterling, R. (1992). "Underground research: Here and there." Civ. Engrg., ASCE, 62(12), 56-58.
    • (1992) Civ. Engrg., ASCE , vol.62 , Issue.12 , pp. 56-58
    • Sterling, R.1
  • 9
    • 0029702961 scopus 로고    scopus 로고
    • Microtunneling database for the USA and Canada from 1984 to 1995
    • ASCE, Reston, Va.
    • Atalah, A., and Hadala, P. (1996). "Microtunneling database for the USA and Canada from 1984 to 1995." Proc., Pipeline Crossings 1996, ASCE, Reston, Va., 332-339.
    • (1996) Proc., Pipeline Crossings 1996 , pp. 332-339
    • Atalah, A.1    Hadala, P.2
  • 10
    • 0344918214 scopus 로고
    • Bureau of Labor Statistics. (1995). ftp://146.142.4.23/pub/special. requests/ocwc/osh/cftb0067.txt.
    • (1995)
  • 11
    • 0344918215 scopus 로고    scopus 로고
    • Soil tests prove key on microtunneling project: Learning by doing: A contractors first microtunneling project
    • Feb.
    • Gokhale, S., and Abraham, D. (1998). "Soil tests prove key on microtunneling project: Learning by doing: A contractors first microtunneling project." Underground Constr., Feb., 31-34.
    • (1998) Underground Constr. , pp. 31-34
    • Gokhale, S.1    Abraham, D.2
  • 13
    • 0343435692 scopus 로고    scopus 로고
    • Trenchless installation of conduits beneath roadways
    • Transportation Research Board, Washington, D.C.
    • Iseley, T., and Gokhale, S. B. (1997). "Trenchless installation of conduits beneath roadways." Synthesis of Hwy. Pract. 242, Transportation Research Board, Washington, D.C.
    • (1997) Synthesis of Hwy. Pract. , vol.242
    • Iseley, T.1    Gokhale, S.B.2
  • 15
    • 0007846868 scopus 로고
    • Design aspects of microtunneling projects
    • Klein, S. J. (1995). "Design aspects of microtunneling projects." No-Dig Engrg., Trenchless Technol., 2(2), 9-12.
    • (1995) No-dig Engrg., Trenchless Technol. , vol.2 , Issue.2 , pp. 9-12
    • Klein, S.J.1
  • 17
    • 0345349414 scopus 로고
    • Contribution of the contract placing-authority to the economic efficiency of microtunneling technology
    • Balkema, Rotterdam, The Netherlands
    • Mohring, K. (1992). "Contribution of the contract placing-authority to the economic efficiency of microtunneling technology." Microtunneling, Balkema, Rotterdam, The Netherlands, 79-89.
    • (1992) Microtunneling , pp. 79-89
    • Mohring, K.1
  • 18
    • 0030108780 scopus 로고    scopus 로고
    • Microtunneling: When, where, and how to use it
    • Mar.
    • Staheli, K., and Hermanson, G. E. (1996). "Microtunneling: When, where, and how to use it." Water Envir. & Technol., Mar., 31-36.
    • (1996) Water Envir. & Technol. , pp. 31-36
    • Staheli, K.1    Hermanson, G.E.2


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.