메뉴 건너뛰기




Volumn 67, Issue 11, 1997, Pages 42-47

An estimate of transportation cost savings from using Intelligent Transportation System (ITS) infrastructure

Author keywords

[No Author keywords available]

Indexed keywords

BUILD ONLY ALTERNATIVE; INTELLIGENT TRANSPORTATION SYSTEM INFRASTRUCTURE; TRANSPORTATION COST SAVINGS;

EID: 0031277854     PISSN: 01628178     EISSN: None     Source Type: Journal    
DOI: None     Document Type: Review
Times cited : (6)

References (11)
  • 1
    • 0003837528 scopus 로고
    • Annual Report, Research Report 1131-7. Texas Transportation Institute, September
    • Urban Roadway Congestion - 1982-1992. Volume 1: Annual Report, Research Report 1131-7. Texas Transportation Institute, September 1995.
    • (1995) Urban Roadway Congestion - 1982-1992 , vol.1
  • 3
    • 84889503620 scopus 로고    scopus 로고
    • note
    • From Ref. 1, added required new freeway and arterial miles together, yielding 4,453 miles multiplied by 10 years and divided by the total existing freeway and arterial miles (Table 8) for a total of 147,647. The result is 4,453 × 10/147,647 = 30.2 percent. The annual growth rates were not compounded to derive the 10-year figures.
  • 4
    • 0003837528 scopus 로고
    • Annual Report, Research Report 1131-7. Texas Transportation Institute, September
    • Urban Roadway Congestion - 1982-1992. Volume 1: Annual Report, Research Report 1131-7. Texas Transportation Institute, September 1995; Table 8. Totaled columns for Additional Annual Lane-Miles needed for Freeways and Principal Arterials needed to maintain 1992 congestion levels. Actual totals were 1,748 for freeways and 2,705 for arterials.
    • (1995) Urban Roadway Congestion - 1982-1992 , vol.1
  • 5
    • 84889528121 scopus 로고
    • Ibid. Totaled columns on average annual lane-miles added to system, 1988-1992 (1,170 for freeways, 1,757 for principal arterials). Built percentages are 1,170/1,748 = 66.9 percent for freeways and 1,757/2,705 = 65.0 percent for arterials.
    • (1995) Urban Roadway Congestion - 1982-1992 , vol.1
  • 6
    • 0013545865 scopus 로고
    • ITE
    • Used lane miles from Ref. 1; used two different estimates for road construction cost and then averaged them: 1) A Toolbox for Alleviating Traffic Congestion, ITE, 1989. Table 4.2 gives construction costs of $2.26 million per lane mile for new freeways for Texas. The high-way construction cost indices in this table indicates that Wisconsin is more of a "typical" state. Therefore, the cost for typical new freeways is calculated at $2.26 million per lane mile multiplied by 317.9/119.3 (cost indices of Texas and Wisconsin), for approximately $6 million per lane mile. Similarly, $0.41 million times 317.9/119.3 yielded approximately $1 million per lane mile for widening a "non-freeway." 2) 1991 HPMS Needs Analysis Urban Construction costs for widening urban highways. A mid-point was taken between costs in built-up and outlying areas for widening existing facilities per added lane-mile. For freeways, built up costs were $3.683 M and outlying were $2.359 M; $3 M was used. For arterials, built up costs were $2.013 M and outlying were $1.394 M; $1.6 M was used. This produced lower total costs for traditional construction.
    • (1989) A Toolbox for Alleviating Traffic Congestion
  • 7
    • 84889554837 scopus 로고    scopus 로고
    • Used lane miles from Ref. 1; used two different estimates for road construction cost and then averaged them: 1) A Toolbox for Alleviating Traffic Congestion, ITE, 1989. Table 4.2 gives construction costs of $2.26 million per lane mile for new freeways for Texas. The high-way construction cost indices in this table indicates that Wisconsin is more of a "typical" state. Therefore, the cost for typical new freeways is calculated at $2.26 million per lane mile multiplied by 317.9/119.3 (cost indices of Texas and Wisconsin), for approximately $6 million per lane mile. Similarly, $0.41 million times 317.9/119.3 yielded approximately $1 million per lane mile for widening a "non-freeway." 2) 1991 HPMS Needs Analysis Urban Construction costs for widening urban highways. A mid-point was taken between costs in built-up and outlying areas for widening existing facilities per added lane-mile. For freeways, built up costs were $3.683 M and outlying were $2.359 M; $3 M was used. For arterials, built up costs were $2.013 M and outlying were $1.394 M; $1.6 M was used. This produced lower total costs for traditional construction.
    • 1991 HPMS Needs Analysis Urban Construction Costs for Widening Urban Highways
  • 8
    • 84889534154 scopus 로고    scopus 로고
    • dividing the 8,129,182 lane miles that existed in 1993 into the $22,907,000 spent in 1993 on Operations and Maintenance
    • Based on 1995 Status of the Nation's Surface Transportation System: Condition and Performance, dividing the 8,129,182 lane miles that existed in 1993 into the $22,907,000 spent in 1993 on Operations and Maintenance (see pages 82 and 186).
    • 1995 Status of the Nation's Surface Transportation System: Condition and Performance , pp. 82
  • 11
    • 3342882561 scopus 로고
    • FHWA Office of Traffic Management and Intelligent Transportation Systems Applications, August
    • Cost Estimate and Assumptions for the CORE Infrastructure. FHWA Office of Traffic Management and Intelligent Transportation Systems Applications, August 1995; estimates a value of 10.1 percent for large cities and 9.1 percent for medium cities; 10 percent was used in this analysis. Note that a key assumption for both capital and O&M costs is a predominantly purchased communications infrastructure. A leased communications assumption would substantially change the split of costs between capital and O&M.
    • (1995) Cost Estimate and Assumptions for the CORE Infrastructure


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.