Volumn 15, Issue 5, 1997, Pages 273-281

Project risk analysis and management - PRAM the generic process

Author keywords

Generic processor; Risk analysis; Risk management

Indexed keywords

PROCESS CONTROL; RISK ASSESSMENT; SUPERVISORY PERSONNEL;

EID: 0031258020     PISSN: 02637863     EISSN: None     Source Type: Journal    
DOI: 10.1016/S0263-7863(96)00079-8     Document Type: Article
Times cited : (145)

References (5)
  • 4
    • 0002210527 scopus 로고
    • A risk engineering approach to project risk management
    • or see Chapman, C. B., A risk engineering approach to project risk management. International Journal of Project Management, 1990, 8(1) 5-16
    • (1990) International Journal of Project Management , vol.8 , Issue.1 , pp. 5-16
    • Chapman, C.B.1
  • 5
    • 0042146238 scopus 로고
    • Reference D/PPP (PM) 2/1/12, published by and obtainable from the Ministry of Defence, Procurement Executive, Directorate of Procurement Policy (Project Management) Room 6302, Main Building, Whitehall, London, SW1A 2HB
    • MOD(PE)-DPP(PM), Risk Management in Defence Procurement, Reference D/PPP (PM) 2/1/12, published by and obtainable from the Ministry of Defence, Procurement Executive, Directorate of Procurement Policy (Project Management) Room 6302, Main Building, Whitehall, London, SW1A 2HB, 1991.
    • (1991) Risk Management in Defence Procurement