Volumn 47, Issue 2, 1995, Pages 119-129

Improving allowed outage time and surveillance test interval requirements: a study of their interactions using probabilistic methods

Author keywords

[No Author keywords available]

Indexed keywords

NUCLEAR POWER PLANTS; OUTAGES; PROBABILITY; RELIABILITY; RISK ASSESSMENT; SECURITY SYSTEMS; SPECIFICATIONS;

EID: 0029207825     PISSN: 09518320     EISSN: None     Source Type: Journal    
DOI: 10.1016/0951-8320(94)00043-N     Document Type: Article
Times cited : (36)

References (9)
  • 1
    • 30244553704 scopus 로고
    • Evaluation of risks associated with AOT and STI requirements at the ANO-1 nuclear power plant
    • Brookhaven National Laboratory, Upton, New York
    • (1988) NUREG/CR-5200
    • Samanta1    Wong2    Carbonaro3
  • 3
    • 30244452728 scopus 로고
    • Analisis de la interaccion entre los requisitos de tiempo maximo permitido de inoperabilidad (AOT) e intervalo entre pruebas de vigilancia (STI) de componentes de sistemas de seguridad de centrales nucleares
    • Chemical and Nuclear Engineering Department, Polytechnic University of Valencia, Spain
    • (1991) Thesis Manuscript
    • Martorell1
  • 4
    • 84919237584 scopus 로고
    • Risk-Based Evaluation of Technical Specifications
    • Electric Power Research Institute, Palo Alto, California
    • (1985) EPRI NP-4317
  • 6
    • 30244539114 scopus 로고
    • Technical specifications action statement requiring shutdown: a risk perspective with application to the RHR/SSW system of a BWR
    • Brookhaven National Laboratory, Upton, New York, and Avaplan Oy, Espoo, Finland
    • (1993) NUREG/CR-5995
    • Mankamo1    Kim2    Samanta3