Volumn 23, Issue 6, 1978, Pages 1000-1005

Optimal Scheduling of Thermal Generating Units

Author keywords

[No Author keywords available]

Indexed keywords

ELECTRIC POWER PLANT EQUIPMENT;

EID: 0018161804     PISSN: 00189286     EISSN: 15582523     Source Type: Journal    
DOI: 10.1109/TAC.1978.1101906     Document Type: Article
Times cited : (73)

References (21)
  • 1
    • 0017481465 scopus 로고
    • Optimal unit commitment
    • Apr.
    • A. Turgeon, “Optimal unit commitment,” IEEE Trans. Automat. Contr., vol. AC-22, pp. 223-227, Apr. 1977.
    • (1977) IEEE Trans. Automat. Contr. , vol.AC-22 , pp. 223-227
    • Turgeon, A.1
  • 2
    • 2542578194 scopus 로고
    • A study of the economic shut down of generating units in daily dispatch
    • Dec.
    • C. J. Baldwin, K. M. Dale, and R. F. Dittrich, “A study of the economic shut down of generating units in daily dispatch,” IEEE Trans. Power App. Syst., vol. PAS-78, pp. 1272-1284, Dec. 1959.
    • (1959) IEEE Trans. Power App. Syst. , vol.PAS-78 , pp. 1272-1284
    • Baldwin, C.J.1    Dale, K.M.2    Dittrich, R.F.3
  • 4
    • 84939719646 scopus 로고    scopus 로고
    • Optimisation du demarrage des moyens de production
    • Direction des Etudes et Recherches
    • E. Scano, “Optimisation du demarrage des moyens de production,” Elecricite de France, Direction des Etudes et Recherches.
    • Elecricite de France
    • Scano, E.1
  • 5
    • 0014551910 scopus 로고
    • Optimum commitment of thermal generating units
    • K. Kawatake, “Optimum commitment of thermal generating units,” Elec. Eng. Japan, vol. 89, no. 8, pp. 69-77, 1969.
    • (1969) Elec. Eng. Japan , vol.89 , Issue.8 , pp. 69-77
    • Kawatake, K.1
  • 6
    • 0014649794 scopus 로고
    • Optimization of start-up and shut-down of thermal units
    • paper O.S.7
    • M. Udo, “Optimization of start-up and shut-down of thermal units,” presented at 2nd Power Syst. Computation Conf., paper O.S.7, 1969.
    • (1969) presented at 2nd Power Syst. Computation Conf.
    • Udo, M.1
  • 8
    • 0015056789 scopus 로고
    • Large-scale hydro-thermal unit commitment—method and results
    • June
    • H. H. Happ, R. C. Johnson, and W. J. Wright, “Large-scale hydro-thermal unit commitment—method and results,” IEEE Trans. Power App. Syst., vol. PAS-90, pp. 1373-1384, June 1971.
    • (1971) IEEE Trans. Power App. Syst. , vol.PAS-90 , pp. 1373-1384
    • Happ, H.H.1    Johnson, R.C.2    Wright, W.J.3
  • 9
    • 0016063998 scopus 로고
    • Scheduling of start-up and shut-down of thermal generating units considering reliability
    • S. Yamashiro, “Scheduling of start-up and shut-down of thermal generating units considering reliability,” Elec. Eng. Japan, vol. 94, no. 3, pp. 87-94. 1974.
    • (1974) Elec. Eng. Japan , vol.94 , Issue.3 , pp. 87-94
    • Yamashiro, S.1
  • 10
    • 67650389898 scopus 로고
    • Optimization of priority lists for a unit commitment program
    • San Francisco
    • K. M. Burns and C. A. Gibson, “Optimization of priority lists for a unit commitment program,” presented at IEEE PES Summer Meeting, San Francisco, 1975.
    • (1975) presented at IEEE PES Summer Meeting
    • Burns, K.M.1    Gibson, C.A.2
  • 11
    • 0015058420 scopus 로고
    • Security constrained unit commitment
    • June
    • J. D. Guy, “Security constrained unit commitment,” IEEE Trans. Power App. Syst., vol. PAS-90, pp. 1385-1390, June 1971.
    • (1971) IEEE Trans. Power App. Syst. , vol.PAS-90 , pp. 1385-1390
    • Guy, J.D.1
  • 12
    • 0015096004 scopus 로고
    • Optimal thermal generating unit commitment
    • June
    • A. K. Ayoub and A. D. Patton, “Optimal thermal generating unit commitment,” IEEE Trans. Power App. Syst. vol. PAS-90, pp. 1752-1756, June 1971.
    • (1971) IEEE Trans. Power App. Syst. , vol.PAS-90 , pp. 1752-1756
    • Ayoub, A.K.1    Patton, A.D.2
  • 13
    • 0006844518 scopus 로고
    • A method for planning economic unit commitment and maintenance of thermal power systems
    • May
    • K. Hara, M. Kimura, and N. Honda, “A method for planning economic unit commitment and maintenance of thermal power systems,” IEEE Trans. Power App. Syst., vol. PAS-85, pp. 427-436, May 1966.
    • (1966) IEEE Trans. Power App. Syst. , vol.PAS-85 , pp. 427-436
    • Hara, K.1    Kimura, M.2    Honda, N.3
  • 14
    • 84937076552 scopus 로고
    • Power generation scheduling by integer programming—development of theory
    • Feb.
    • L. L. Garver, “Power generation scheduling by integer programming—development of theory,” IEEE Trans. Power App. Syst., vol. PAS-82, pp. 730-735, Feb. 1963.
    • (1963) IEEE Trans. Power App. Syst. , vol.PAS-82 , pp. 730-735
    • Garver, L.L.1
  • 15
    • 84921122504 scopus 로고
    • An application of mixed-integer programming duality to scheduling thermal generating systems.
    • Dec.
    • J. A. Muckstadt and R. C. Wilson, “An application of mixed-integer programming duality to scheduling thermal generating systems.” IEEE Trans. Power App. Syst., vol. PAS-87, pp. 1968-1978, Dec. 1968.
    • (1968) IEEE Trans. Power App. Syst. , vol.PAS-87 , pp. 1968-1978
    • Muckstadt, J.A.1    Wilson, R.C.2
  • 16
    • 84939727320 scopus 로고
    • Méthode combinatoire de repartition a court terme d'un ensemble de moyens de production thermique hydraulique
    • P. Martin and A. Merlin, “Méthode combinatoire de repartition a court terme d'un ensemble de moyens de production thermique hydraulique,” R.I.R.O., vol. 4, pp. 77-96, 1970.
    • (1970) R.I.R.O. , vol.4 , pp. 77-96
    • Martin, P.1    Merlin, A.2
  • 18
    • 9644308639 scopus 로고
    • Partitioning procedures for solving mixed variables programming problems
    • J. F. Benders, “Partitioning procedures for solving mixed variables programming problems,” Numerische Mathematik, vol. 4, pp. 238-252, 1962.
    • (1962) Numerische Mathematik , vol.4 , pp. 238-252
    • Benders, J.F.1
  • 19
    • 0000703172 scopus 로고
    • Generalized Lagrange multiplier method for solving problems of optimum allocation of resources
    • H. Everett, III, “Generalized Lagrange multiplier method for solving problems of optimum allocation of resources,” Oper. Res., vol. 11, pp. 399-417, 1963.
    • (1963) Oper. Res. , vol.11 , pp. 399-417
    • Everett, H.1
  • 20
    • 0017495536 scopus 로고
    • Optimal power dispatch—a comprehensive survey.
    • May
    • H. H. Happ, “Optimal power dispatch—a comprehensive survey.” IEEE Trans. Power App. Syst., vol. PAS-96, pp. 841-854, May 1977.
    • (1977) IEEE Trans. Power App. Syst. , vol.PAS-96 , pp. 841-854
    • Happ, H.H.1
  • 21
    • 84942008101 scopus 로고
    • Optimal scheduling of thermal generating units
    • Nov.
    • A. Turgeon, “Optimal scheduling of thermal generating units,” presented at TIMS/ORSA Conference, Atlanta, Nov. 1977.
    • (1977) presented at TIMS/ORSA Conference
    • Turgeon, A.1


* 이 정보는 Elsevier사의 SCOPUS DB에서 KISTI가 분석하여 추출한 것입니다.